Construction
The following provides a general timeline of the milestones along the way regarding the Expansion and Enclosure Project being undertaken.  Please note that some of the entries have links to images or documents that are only viewable when you are logged into the website.
  • June 17, 2019 - the office of the Assistant General Manager (Nelenie Aronce) has been moved to its new permanent location in the left half of what was the office of the Customer Service Coordinator (Carol Garbarino).
  • May 24, 2019 - initial demolition of the old Manager's office, concrete pad, exterior Billiards Room wall and breezeway structure between the main buildings has been completed.
  • April 22, 2019 - Ceremonial Ground Breaking.
  • April 19, 2019 - the offices of the General Manager (Damian Carrasco), Lifestyle Director (Debbie Kent) and Breeze editor (Trish Williamson) have been relocated to the trailer in the parking lot; the front and Lintwhite/Lanneret entrances are closed with entry into the Vista Room, Kitchen, other Management Offices, Social Hall, Craft Rooms, Pool area, Fitness Room and Fitness Studio are provided for as indicated:
  • April 12, 2019 - the Billiards Room has been cleared; the Computer/Library Room has been cleared and the computers stored; the Lobby area to the east of the Vista Room is closed; the Activity Room has been closed; and the bicycle rack has been moved to the center of the Bocce courts.
  • April 4, 2019 - the City of North Las Vegas finalized the engineering documents and issued the necessary permits to MK House Consulting.
  • March 8, 2019 - removal of landscaping and rerouting of irrigation lines in the areas that will be affected by construction was completed by Gothic Landscaping - the work began on February 28, 2019.
  • March 1, 2019 - storage containers that will be used to store the contents of the Library and furniture from various rooms that will be impacted by the construction were delivered.
  • February 25, 2019 - the trailer that will be used by Sun City Aliante staff members and the MK House Consulting project manager was delivered.  At the same time, displaced handicap parking spaces were relocated.
  • December 3, 2018 - MK House Consulting submitted the engineering documents to the City of North Las Vegas for permit approval.
  • November 14, 2018 Board Meeting - the Board reviewed the final design as proposed by the Ad Hoc Committee, MK House Consulting and JVC Architects, including a number of conceptual drawings, A&E documents and final proposed project costs.  The Board approved the final design and project costs.  General plans, conceptual drawings/images and an animated overview of the completed project have been made available for review by Sun City Aliante residents.
  • August - October 2018 - the Ad Hoc Committee worked with MK House Consulting and JVC Architects to finalize the design and other project requirements.  Development of the design included:
  1. Overall concept of the Expansion/Enclosure
  2. Concept of the Expansion/Enclosure with emphasis on the Management Offices
  3. Option of relocating the Activities/Fitness Offices, Computer Room and Library
  • June 4, 2018 - JVC Architects began development of the Architectural and Engineering (A&E) documents.
  • May 10, 2018 - the contract was signed by MK House Consulting and the Board.
  • March 29, 2018 - the initial draft of the contract was presented to the Board.
  • March 14, 2018 Board Meeting - the Board selected MK House Consulting as the general contractor for the development of the concept.
  • February 22, 2018 - the Ad Hoc Committee interviewed two bidders and developed a recommendation for the Board.
  • February 15, 2018 - the Ad Hoc Committee met to review the bids and begin the development of a recommendation.
  • February 14, 2018 Board Meeting - the bids were opened, reviewed and forwarded to the Ad Hoc Committee for review and recommendation.
  • January 22, 2018 - the RFP was finalized and sent out for bids with a bid due date of February 12, 2018.
  • January 10, 2018 Board Meeting - the draft RFP for the Clubhouse expansion/enclosure project and the related presentation were presented to the Board.  The project to develop a concept for the expansion/enclosure of the Community Center was approved.
  • November 8, 2017 Board Meeting - the draft RFP for expanding the Billiards and Activities Rooms was presented to the Board.  The Board requested that the Ad Hoc Committee develop a parallel RFP to develop a conceptual framework to include both expansion of the Billiards and Activities Rooms and creation of a new main entrance to the Community Center.
  • August 9, 2017 Board Meeting - the Board authorized an Ad Hoc Committee to develop an RFP for expanding the Billiards and Activities Rooms.  At the same meeting, the Board authorized the Ad Hoc Committee to study the feasibility of enclosing the breezeway and creating a new main entrance to the Community Center.