Construction
The following provides a general timeline of the major milestones along the way regarding the Expansion and Enclosure Project being undertaken.  Please note that some of the entries have links to images or documents that are only viewable when you are logged into the website.
 
  • In the near future, a lot of activity will start happening around the Community Center, including:
    • April 12, 2019 - Billiards Room is scheduled to close.
    • April 12, 2019 - Library and Computer Room is scheduled to close.
    • April 16, 2019 - Lobby area outside the Vista Room is scheduled to close.
    • April 18, 2019 - Activities Room is scheduled to close.
  • In addition, various restrictions related to entering/exiting the Community Center will include:
    • Front Entrance Closure - when the front entrance is blocked, entry into the Vista  Room, Kitchen, Management Offices, Social Hall, Craft Rooms, Pool area, Fitness Room and Fitness Studio will be provided for as indicated:
      • Vista Room, Kitchen & Management Offices - through the single entrance near the Kitchen (handicapped accessible).
      • Social Hall & Craft Rooms - through the double doors opposite the Bocce Courts (that door is locked at 6 p.m. unless otherwise specified).
      • Pool area, Fitness Room & Fitness Studio - through the gate on the Golf Course end of the building, into the Court Yard and through the double doors on the left (handicapped accessible).
    • Back Entrance Closure - the Community Center will not be accessible via the pathway from Lintwhite/Lanneret Street.
  • Management Offices:
    • General Manager (Damian Carrasco), Lifestyle Director (Debbie Kent) and the Breeze editor (Trish Williamson) will be housed in the trailer located in the parking lot.
    • Assistant General Manager (Nelenie Arance) will be moved to her new office just to the west of her current office.
  • April 12, 2019 - the Billiards Room has been cleared; the Computer/Library Room has been cleared and the computers stored.
  • April 4, 2019 - the City of North Las Vegas finalized the engineering documents and issued the necessary permits to MK House Consulting.
  • March 8, 2019 - removal of landscaping and rerouting of irrigation lines in the areas that will be affected by construction was completed by Gothic Landscaping - the work began on February 28, 2019.
  • March 1, 2019 - storage containers that will be used to store the contents of the Library and furniture from various rooms that will be impacted by the construction were delivered.
  • February 25, 2019 - the trailer that will be used by Sun City Aliante staff members and the MK House Consulting project manager was delivered.  At the same time, displaced handicap parking spaces were relocated.
  • December 3, 2018 - MK House Consulting submitted the engineering documents to the City of North Las Vegas for permit approval.
  • November 14, 2018 Board Meeting - the Board reviewed the final design as proposed by the Ad Hoc Committee, MK House Consulting and JVC Architects, including a number of conceptual drawings, A&E documents and final proposed project costs.  The Board approved the final design and project costs.  General plans, conceptual drawings/images and an animated overview of the completed project have been made available for review by Sun City Aliante residents.
  • August - October 2018 - the Ad Hoc Committee worked with MK House Consulting and JVC Architects to finalize the design and other project requirements.  Development of the design included:
  1. Overall concept of the Expansion/Enclosure
  2. Concept of the Expansion/Enclosure with emphasis on the Management Offices
  3. Option of relocating the Activities/Fitness Offices, Computer Room and Library
  • June 4, 2018 - JVC Architects began development of the Architectural and Engineering (A&E) documents.
  • May 10, 2018 - the contract was signed by MK House Consulting and the Board.
  • March 29, 2018 - the initial draft of the contract was presented to the Board.
  • March 14, 2018 Board Meeting - the Board selected MK House Consulting as the general contractor for the development of the concept.
  • February 22, 2018 - the Ad Hoc Committee interviewed two bidders and developed a recommendation for the Board.
  • February 15, 2018 - the Ad Hoc Committee met to review the bids and begin the development of a recommendation.
  • February 14, 2018 Board Meeting - the bids were opened, reviewed and forwarded to the Ad Hoc Committee for review and recommendation.
  • January 22, 2018 - the RFP was finalized and sent out for bids with a bid due date of February 12, 2018.
  • January 10, 2018 Board Meeting - the draft RFP for the Clubhouse expansion/enclosure project and the related presentation were presented to the Board.  The project to develop a concept for the expansion/enclosure of the Community Center was approved.
  • November 8, 2017 Board Meeting - the draft RFP for expanding the Billiards and Activities Rooms was presented to the Board.  The Board requested that the Ad Hoc Committee develop a parallel RFP to develop a conceptual framework to include both expansion of the Billiards and Activities Rooms and creation of a new main entrance to the Community Center.
  • August 9, 2017 Board Meeting - the Board authorized an Ad Hoc Committee to develop an RFP for expanding the Billiards and Activities Rooms.  At the same meeting, the Board authorized the Ad Hoc Committee to study the feasibility of enclosing the breezeway and creating a new main entrance to the Community Center.